Data Centre Construction Cost Guide Data Centre Construction Cost Guide

Asia Pacific Data Centre Construction Cost Guide 2023/24

Access the guide

Asia Pacific is attractive to investors for its comparatively low land and development costs and for the growth potential in both developed and emerging markets. 
Regional Land Cost Index - Top 5 Markets
An increasing scarcity of suitable land parcels with available power in some markets, combined with higher borrowing costs in most markets, have contributed to cost increases. The top 5 most expensive markets for land cost are:

Regional Construction Cost Index - Top 5 Markets
With year-on-year increases of between 8% in Singapore and 3.5% in Australia, the top 5 most expensive markets for construction cost are:
 


Although supply chain disruption and supply/demand imbalances for both labour and materials remain in recovery, raw material prices, energy and transport costs remain at an all-time high and continue to contribute towards record construction costs. Overall, the market has seen an average increase of 4.9% on 2022 construction pricing.

ASIA PACIFIC DATA CENTRE CONSTRUCTION COST GUIDE 2023/24

Cushman & Wakefield’s inaugural Data Centre Construction Cost Guide 2023/24 provides a comprehensive analysis of both land purchase and data centre construction costs across Asia Pacific, as well as a schedule of land banking rates and a summary of key trends within the sector.
ACCESS THE GUIDE External Link

CONTACTS

James Normandale
James Normandale

Head of Asia Pacific Data Centre Construction, Project Development Services
Singapore


65 90493753

Download VCard

Vivek Dahiya
Vivek Dahiya

Managing Director & Head - Data Centre Advisory Team, Asia Pacific
Gurgaon, India


Download VCard

Christine_Ho_640x640
Christine Ho

Associate Director, Client Services
Singapore, Singapore


Download VCard

Pritesh-Swamy
Pritesh Swamy

Director, Data Center Research & Advisory
Mumbai, India


+91 (O22) 42231600

Download VCard

Dominic-Brown_Headshot_AP
Dominic Brown

Head of International Research, Global Think Tank
Brisbane, Australia


+61 (431) 947161

Download VCard

Rebecca Jung
Rebecca Jung

Associate Director, Business Development ServicesAssociate Director, Business Development Services
Sydney, Australia


+61 (2) 82439915

Download VCard

Related articles

Data-Center-Update_APAC_web-card-1221
Research

APAC Data Centre Update

The operational capacity of Asia Pacific’s* data centre markets has surpassed the 10GW mark, with ~800MW of new supply added in H2 2023 bringing the total regional live capacity up to 10.6GW. We continue to witness a robust development pipeline with 3.9GW under construction throughout the region and 9.4GW in planning stages, which is an increase of ~900MW since our last update.
2/15/2024
Hotel Construction
Data centre construction cost increases of up to 8% across region year-over-year but development shows no sign of pausing

Japan has been named the most expensive market for data centre construction while Singapore has topped the rankings for the most expensive land costs in Asia Pacific, according to a new report.

Amy Kathleen Kelly • 11/6/2023

Colocation
Insights

Why go COLO?

Migrating to a colocation (colo) data centre can help with long term costs savings, ensure 24/7 reliability with minimal power interruptions, achieve higher sustainability and flexibility in line with your business goals.
Vivek Dahiya • 5/25/2023
Data Centre India webinar
Insights

Data Centres | The future of Colocation

Organizations across the world are evolving their flexible work environments by moving their workloads into a mix of on-premises, colocation setups, public cloud, or private cloud solutions. 
Vivek Dahiya • 8/16/2022
Insights

$name

$name

クッシュマン・アンド・ウェイクフィールドでは、トラフィックの分析および本ウェブサイト上でベストの体験をお客様に提供するためクッキーを使用します。このダイアログを閉じ、お客様の同意を確認されるか、詳細については次のページを訪れてください:
クッキー通知

その他のオプション
同意する
これらのクッキーにより、当社のウェブサイトが期待通りに動作することが保証されます。例えば、ウェブサイトのトラフィック負荷を当社のサーバー間で分散し、使用量が特に多いときにウェブサイトがクラッシュしないようにします。
これらのクッキーは、お客様が行った選択(ユーザー名、言語、居住地域など)をウェブサイトに記憶させ、より充実した機能を提供するためのものです。これらのクッキーは、広告に使用される可能性のあるお客様の情報を収集したり、お客様がインターネット上でどこにいたかを記憶したりすることはありません。
これらのクッキーは、当社がマーケティングパートナーと協力して、お客様が当社のウェブサイトに訪問する前にどの広告やリンクをクリックしたかを理解したり、当社の広告をお客様にとってより適切なものにするために使用されます。
すべてに同意する
すべてを拒否する
設定の保存