Data centre construction cost increases of up to 8% across region year-over-year but development shows no sign of pausing

Amy Kathleen Kelly • 06/11/2023
  • Average construction cost increase of 4.9% across Asia Pacific key markets

  • Mature markets dominate data centre land, construction cost indexes

  • Data centre development activity across the region remains “significantly elevated”

Japan has been named the most expensive market for data centre construction while Singapore has topped the rankings for the most expensive land costs in Asia Pacific, according to a new report.

Mature markets dominated the top five positions for both the Regional Construction Cost Index and the Regional Land Cost Index included in Cushman & Wakefield’s inaugural Data Centre Construction Cost Guide.

Report author and Head of Asia Pacific Data Centre Construction, Project Development Services, James B. Normandale said:

“The market is facing some of the highest development rates in data centre market history. This is the result of persistent – although improved – supply chain disruption and construction market inflation, as well as higher capital lending rates across most markets within Asia Pacific. Despite the increased costs, development activity across the region remains significantly elevated as the sector continues to grow in response to secular trends, industry incentives, regulatory relaxation, and interest from investors who see opportunity in the disparity between future population needs and existing IT capacity.”

Figure-1-Regional-Construction-Cost-Index
Based on a medium specification, 10-50MW data centre build (refer p19 of report).

Demand and domestic pressures influence land cost

Singapore’s limited land supply and government restrictions on data centre development saw the city-state top South Korea, Hong Kong China, Japan and mainland China for the most expensive market for land cost. The Regional Land Cost Index was calculated based on suburban industrial land (medium range) rather than central business district (high range) or industrial outskirts (low range) and based on the average cost of key cities within a market. Among a comparison of cities (see Figure 3), Singapore recorded the top price of USD11,573 per square metre (sqm), above Seoul (USD10,525) and Busan (USD8,865).

Figure-2-Regional-Land-Cost-Index
Based on suburban industrial land and averaged across key cities within a market (refer p15 of report).

Development costs elevated overall

The average construction cost increase on 2022 was 4.9% across Asia Pacific. Singapore recorded the greatest increase (8%), while Australian and New Zealand recorded the smallest increase (3.5%).

Figure-3-Land-Cost-by-City-v2
Based on suburban industrial land (medium range) where available (refer p15).

Key Trends Impacting the Data Centre Sector

  • Power, Location & Management
    The rise of AI and ML, while still in its infancy, is expected to drive substantial changes within the data centre sector. These technologies are increasing power consumption, rack loading requirements, and overall site capacity. Unlike traditional data centres, AI data centres for remote learning can be built between 450km and 1,000km from established data centre locations using existing low-latency infrastructure. While this may help to relieve pressure on land and power in densely populated areas, it could create labour and supply chain challenges.
  • Environmental, Social & Governance (ESG)
    There is a growing emphasis on holistic performance measurement within the sector, encompassing financial performance, ethical conduct, societal contributions, and environmental responsibility. Data centre operators are experimenting with sustainable power and zero-carbon electricity options, resulting in operational improvements and cost savings. The adoption of AI-driven software for data centre operations has started to demonstrate improvements in Power Usage Effectiveness (PUE) ratios.
  • Strategic Sourcing & Supply Chain
    Though improved, supply chain disruption driven by geopolitical uncertainty and economic unpredictability continues to impact costs. This trend is expected to persist into 2024 and has prompted the sector to adopt more conservative approaches to material and resource planning, such as multi-vendor supplier strategies.

“The data centre sector in Asia Pacific is in a dynamic phase as it undergoes further growth and innovation. The colocation market size was reported to be USD25.5 billion in 2022 and it is expected to reach USD51.8 billion by 2028 – a Compound Annual Growth Rate of 12.5%. Hyperscale cloud revenue is expected to grow at 19% CAGR through now and 2028. Investors who stay abreast of developments in the AI and ML space will be well-placed to capitalize on these growth opportunities,” said Mr. Normandale.

About the Asia Pacific Data Centre Construction Cost Guide 2023

The guide tracks 37 key data centre locations across Asia Pacific with a comprehensive breakdown of costs covering land acquisition, advanced land clearance and demolition works, base build and fit-out construction costs. It offers a comprehensive analysis of the Asia Pacific data centre landscape, including key trends that are shaping the region's data centre sector. This is the first year that Cushman & Wakefield has published its data centre development cost data. Read the Asia Pacific Data Centre Construction Cost Guide here.

Recent Press Releases

handshake
Cushman & Wakefield Appointed by Standard Chartered Bank to Deliver Property Services across Asia and Global Asset and Transaction Management

Cushman & Wakefield (NYSE: CWK), a leading global real estate services firm, announces that it has been appointed by Standard Chartered Bank (the Bank) to provide services to support its Asia workplace transformation, and Global Asset and Transaction Management for the Bank’s 11m square foot global real estate portfolio.

Chek Yee Foo • 18/04/2024

investment sales singapore 2024
Total investment sales could surpass $25.0b in 2024, higher than $19.2b in 2023

According to Cushman & Wakefield’s latest Marketbeat report, Investment volumes are up by 20.9% yoy.

Nandhini Rad • 08/04/2024

Cititech-Industrial-Building-CardImg
Prime Freehold Strata Industrial Units for Sale at Cititech Industrial Building and Citilink Warehouse Complex

ERA Realty Network Pte Ltd (ERA), Cushman & Wakefield (NYSE: CWK), and JLL (NYSE: JLL) have been jointly appointed as the exclusive marketing agents for the sale of freehold strata light industrial units at Cititech Industrial Building and Citilink Warehouse Complex. 

Nandhini Rad • 08/04/2024

12 Joan Road
Large Good Class Bungalow Site with Two Bungalows at Caldecott Hill for sale at $62.8 million: Cushman & Wakefield

Cushman & Wakefield (“C&W”), as the exclusive marketing agent, is pleased to present for sale a pair of adjacent freehold bungalows (collectively the “Property”) situated on a single Good Class Bungalow (“GCB”) site at Joan Road, in the prestigious Caldecott Hill Estate via an Expression of Interest (“EOI”) exercise. The indicative price is $62.8 million (approx. $1,599 psf).

02/04/2024

Natalie Craig
Cushman & Wakefield announces country CEO position, appoints Natalie Craig

Cushman & Wakefield [NYSE: CWK], a global leader in real estate services, is proud to announce the appointment of Natalie Craig into the newly created position of Singapore CEO, effective April 1, 2024.

Nandhini Rad • 27/03/2024

OneTen-Paya-Lebar
Hwa Hong Corporation Limited successfully sells OneTen Paya Lebar

Cushman & Wakefield (NYSE: CWK) and Savills (NYSE: Savills) are pleased to announce that Hwa Hong Corporation Limited, represented by Cushman & Wakefield and Savills, has successfully completed the sale of OneTen Paya Lebar, a rare freehold city fringe data center located in Paya Lebar.

Nandhini Rad • 06/03/2024

handshake (image)
State of Flex
STATE OF FLEX - Singapore

2020 and 2021 has been a stress test for the co-working scene as occupiers re-examined the role of the office amidst the rise of remote working and cost containment during the pandemic.

Xian Yang Wong • 20/12/2021

With your permission we and our partners would like to use cookies in order to access and record information and process personal data, such as unique identifiers and standard information sent by a device to ensure our website performs as expected, to develop and improve our products, and for advertising and insight purposes.

Alternatively click on More Options and select your preferences before providing or refusing consent. Some processing of your personal data may not require your consent, but you have a right to object to such processing.

You can change your preferences at any time by returning to this site or clicking on Privacy & Cookies.
MORE OPTIONS
AGREE AND CLOSE
These cookies ensure that our website performs as expected,for example website traffic load is balanced across our servers to prevent our website from crashing during particularly high usage.
These cookies allow our website to remember choices you make (such as your user name, language or the region you are in) and provide enhanced features. These cookies do not gather any information about you that could be used for advertising or remember where you have been on the internet.
These cookies allow us to work with our marketing partners to understand which ads or links you have clicked on before arriving on our website or to help us make our advertising more relevant to you.
Agree All
Reject All
SAVE SETTINGS